中压电缆敷设施工方案(英文版).docx
《中压电缆敷设施工方案(英文版).docx》由会员分享,可在线阅读,更多相关《中压电缆敷设施工方案(英文版).docx(14页珍藏版)》请在课桌文档上搜索。
1、METHODSTATEMENTFORMVCablePullingandInstallation中压电缆敷设施工方案CONTENTS目录1. .SCOPE32. DEFINITIONS33. HEALTHANDSAFETY34. OPERATION45. INSTALLATIONANDFIXATION46. RESPONSIBILITIES90 PROJECTMANAGER90SITEENGINEER100 FOREMAN100 SAFETYENGINEER110 TECHNICIANFROMSUPPILER110 STOREKEEPER127. MANPOWERREQUIRED128. MAT
2、ERIALSREQUIREMENTS129. EQUIPMENTSREQUIREMENTS1310. WASTEMANAGEMENT1411. SPECIALCONTROLMEASURES1412. SUPPORTINGDOCUMENTATION1413. DISTRIBUTION15!.SCOPE Thisproceduretoclearthemethodofthesupply,InstallationsandPullingofMVCable. ThisdocumentdetailsInstallationandPullingofMVCable: Preparationofwork. Del
3、iveryandinspectionuponarrivalofmaterialatsite. Installationofthesystem.2. DEFINITIONSPQP:ProjectQualityPlanPSP:ProjectSafetyPlanQCP:QualityControlProcedureHSE:Health,SafetyandEnvironmentMS:MethodStatementITP:InspectionTestPlanQA/QC:QualityAssurance/QualityControlEngineer.WIR:InspectionandTestRequest
4、MIR:MaterialVerificationRecord.3. HEALTHANDSAFETY StrictlyfollowedasperthemanufacturersHealthandSafetyrecommendationsforhandlinganduseofthematerials. Ensureallinvolvedpersonnelshallbeawareofthesame. Specificsafetymeasureshavetofollowasapplicable,andallthesafetymeasuresarecoveredseparatelyintheprojec
5、tsafetyplan.4. OPERATION MateriaI: MaterialusedW川beasapprovedbytheEngineer. ThesizesandroutesroutingwillbeaspertheapprovedShopDrawings. StOraandProtection: Delivercomponentspartstosite,completelyidentifiedinaccordancewithshopandcertifiedCADDrawingspreparedforthiswork. Storeinaccordancewiththemanufac
6、turersinstructions,aboveground,properlyprotectedfromtheweatherandconstructionactivities.5. INSTALLATIONANDFIXATION Pre-Installation: Allmaterialsanddocumentationrelevanttothisparticularsectionofworkswillbecheckedandverifiedensuringthatthesearecorrectandapprovedtype. Priortothecommencementofworks,ens
7、urethattheareasforpermanentinstallationareready,accessibleandinsuitablecondition.Excavation: PermittoWork(PTW)shallberaisedfortheexcavationclearlymentioningthelocationofwork,sizeofexcavationandlevels. Excavationsareashallbesurveyedandmarkedtothelinesandlevelsasshownonthedrawings. Theareaofexcavation
8、willbecordonedoffusingsafetydevices. EnsuretheworkingareaatanyconfinedspaceisfreefromanyHazardousGasbyproperGastestingusingtheGastestinginstrument. Materials: Notnecessaryfortheconstructionshallberemovedcarefullyandstoredneatlyforreinstatingaftertheconstructionworks. Thematerialreceivedfromtheclient
9、shallbestoredindesignatedareaofstore. Arrangementsshallbemadetoprotectagainsteffectsofweatherandenvironment. Pulling: Insulationresistanceofthecablesshallbecheckedbeforelayingcables. Afterthetest,theendofthecableshallbesealedtopreventtheingressofmoisture. 1.ocationofthepanels/equipmentshallbeidentif
10、ied. Cablesshallbelubricatedifbendsinconduitsareencounteredinaruntofacilitatedrawingin.Cablesmustnotbebenttoaradiusoflessthan12timestheoveralldiameterofthecable. Rollersmustbeusedwherecablesareinstalledinanopentrenchusingapullingropeandeye;cablerollersaretobeusedatfrequentintervalstosupportthecables
11、andmustneverbemorethan3metersapart. Therollersaretobeplacedsecurelytopreventmovement. Thepullingropemustbeequippedwithaswivelandbeattachedtothecablebyastockinggripwithpullingeye. Thecabledrumintendedforcablepullingshallbeidentifiedasperthatindicatedinthedrumschedule. Thecabledrumsshallbeun-packedand
12、placedonacableroller,asrequired. Cablelayingwillgenerallystartfromoneendoftheroutelengthoratanysuitablepoint,asnecessary. Dependingontheweightandsizeofthedrum,suitablesizeofthecablerollingshaft(Spindle)shallbeplacedinsidethecentralaxisofthedrum. Suitablejacksshallbeplacedfirmlyonthegroundandjackedup
13、toallowclearancefromthegrounddependingonthesizeofthecabledrum. Thedrumshallbeliftedbyrequiredequipmentandplacedonthejacks. Thecabledrumwillbecorrectlypositionedandthedirectionofcablepullingasindicatedbyarrowonthedrumshallbecomplied. Thecableshallbedrawnintothetrenchsmoothlywithaminimumofstopsandatan
14、averagespeedofbetween9-12metersperminute,toavoidirregularmovement. Termination: Terminationpointinsidethepanels/equipmentshallbeconsideredforsuitablesparelengthtobeleftavailableduringpullingofcabletermination. AftercuttingthecabletotherequiredlengththeterminationworkwillbeconductedasperADDCStandard.
15、 JointingandTerminationwillbecarriedoutasperADDCstandards.Alljointingandterminationworkwillbecarriedoutbytrainedtechnicians,experiencedinsuchworkfortheoperatingvoltageconcerned. Propercrimpingtoolsshallbeusedcompressiontypelugs.Allcablesaretobeterminatedusedglandsofpropertypeandsizeasperareaclassifi
16、cation. Theglandshallbeassembledstrictlyinaccordancewithmanufacturersinstruction,particularattentionbeingpaidtoensuregoodmechanicalandelectricalcontactbetweenpartwithoutexcessivestrainordistortionofcable. Theentirebodyofthecablemustenterthegland.Thecableshallbeonastraightaxisfromapointatleastsixdiam
17、eterbeforeenteringthegland.Sealsshallbecheckedforcorrectsizeatthepointofapplication. Unusedcableentriesshallbeclosedwithplugsuitableforthedegreeofprotectionclassification.AftercompletionofindoorandoutdoorterminationthecableisreadyforTesting. Commissioning: Thefollowingcalibratedtestinginstrumentswil
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- 压电 敷设 施工 方案 英文

链接地址:https://www.desk33.com/p-981832.html