钻井现场施工指令.ppt
《钻井现场施工指令.ppt》由会员分享,可在线阅读,更多相关《钻井现场施工指令.ppt(50页珍藏版)》请在课桌文档上搜索。
1、GAME PLAN现场施工指令,GAME PLAN,主 要 内 容,一、概述二、开钻前验收三、一开作业四、二开作业五、三开作业六、四开作业七、五开作业八、完井作业,一、概 述,施工井类型:水井、采油井、取心井、修井、探井施工流程:开钻前准备、各开次钻井、完井,沙特钻井特点:以日费形式结算 甲方安排住井监督 甲方全权负责生产,派工单指生产管理人员向生产人员派发生产指令之单据,GAME PLAN,主 要 内 容,一、概述二、开钻前验收三、一开作业四、二开作业五、三开作业六、四开作业七、五开作业八、完井作业,二、开钻前准备,验收单开钻准备开钻前安全会,二、开钻前准备,验收单:,设备的安装安全设施的安
2、装报警器系统的安装钻井液的准备钻具的准备,二、开钻前准备,开钻准备:,校井架地面管线试压测试振动筛测试套管扶正台,二、开钻前准备,开钻前安全会:,Introduce the well Job safety analysis CONDUCT:H2S Drill BOP Drill FIRE Drill,GAME PLAN,主 要 内 容,一、概述二、开钻前验收三、一开作业四、二开作业五、三开作业六、四开作业七、五开作业八、完井作业,三、一开作业,包 括:,钻头 钻具组合 钻井参数 技术交底 下套管前准备 下套管和固井,三、一开作业,技术措施:,WHEN SPUD-IN,DRILL WITH LO
3、W PARAMETERSUSE SPUD MUD WHILE DRILLING 22 HOLEINCREASE FLOW RATE AS REQUIRED TO CLEAN HOLE AFTER REACH 60 CSG PTDO NOT PULL BIT OUT OF CELLARWORK PIPE CAREFULLY TO AVOID HOLE COLLAPSE,三、一开作业,下套管和固井:,RUN 18-5/8”CSGHALLIBURTON R/U CEMENT LINES,WATER LINESENSURE CELLAR PUMPS WORKING PROPERLY ALL TIMES
4、 DURING CEMENTINGIF CEMENT RETURNS AT CELLAR,STOP PUMPING CEMENTDISPLACE CEMENT SLURRY WITH WATER.CLEAN CELLAR FROM CEMENTIN CASE THERE IS NO CMT RETURNS WILL PERFORM TOP CEMENT JOB,GAME PLAN,主 要 内 容,一、概述二、开钻前验收三、一开作业四、二开作业五、三开作业六、四开作业七、五开作业八、完井作业,四、二开作业,钻具组合:(三扶正器刚性满眼钻具组合),16“BIT(NOZ:4x18)+16 NBRR(
5、with FLOAT+TOTCO Ring)+12 SHOCK SUB+16 STRR+1 X 9.5 DC+16 STRR+2 X 9.5 DC+X/OVER+9 X 8-1/4 DCS+8 JAR+2 X 8-1/4 DCS+X/OVER+15 x 5 HWDP+DP TO SURFACE,四、二开作业,技术措施:,RIH&TAG TOP CEMENT(ESTD 50)HYDRO TEST 18-5/8 CASING W/WA TER.OBSERVE 5 MINUTESCONTINUE DRILL 16 HOLE WITH SPUD MUDINCREASE TO OPTIMUM DRILL
6、ING PARAMETERSPUMP HIVIS EVERY STAND 2TIME(30 BBLS)REAM EVERY STAND 2 TIMEWIPER TRIP TO SHOE,RUN BACK TO BOTTOM,REAM AND WIPE ANY TIGHT ZONESWEEP HOLE WITH 100 BBLS OF HIVIS&CHC-SPOT 300 BBLS HIVIS ON BOTTOM BEFORE POOH,四、二开作业,RUNNING CASING:,R/U Casing Handling Equipment for 13-3/8 casing string Ho
7、ld PJSM and discuss Casing Running Procedure&Hazards RIH with casing string Tack-weld the first 5 connections of casing Fill up every 5 joints of casing Run casing to bottom,Circulate 1.25 x Casing capacity w/Rig Pumps 900 GPM,四、二开作业,CEMENTING:,Hold PJSM with crew while circulating hole cleanRig up
8、cementing linesFlush lines to rig floor with 30 bbls of waterEnsure Cement and Rig lines are connected such that pumping&switching over without knocking off lines is achieved.Pressure-test lines to 2500 psiCement as per cement program,四、二开作业,NIPPLE UP BOP:,After Cement,laying down cement head and li
9、nesCentre the wellhead using landing joint and weld between landing base and 18-5/8”casing headN/up 13-5/8 BOP stack and test stack as per Aramco Standard-low(300 psi)/high(3000 psi)testsEnsure that the Valve handles are pointing towards the North before tightening,四、二开作业,TEST BOP:,Connect TDS and 5
10、 drill pipe with 13-3/8 test plug Set 13-3/8 test plug landing base(make sure no leaking)Fill in pipe anuular W/waterClose 5 BOP upper pipe ram and IBOP of TDS Test upper pipe ram as per ARAMCO standard,Test upper pipe ram or hydril,四、二开作业,TEST BOP:,M/U 5 drill pipe and 13-3/8 test plug RIH and set
11、13-3/8 test plug L/base(make sure no leaking)Break out 5 drill pipe from 13-3/8 test plug Pull out of 5 DPFill in hole W/waterClose blind or shear ram Test blind or shear ram as per ARAMCO standard,Test blind or shear ram,四、二开作业,TEST BOP:,Connect TDS and 5 drill pipe with 13-3/8 test cupRIH inside 1
12、3-3/8 casing with test cupFill in hole W/waterClose 5 BOP lower pipe ram and IBOP of TDSTest lower pipe ram as per ARAMCO standard,Test lower pipe ram,GAME PLAN,主 要 内 容,一、概述二、开钻前验收三、一开作业四、二开作业五、三开作业六、四开作业七、五开作业八、完井作业,五、三开作业,PREPARE WORK:,L/down 9-1/2 DC from the derrick Drift all tools and DC and DP
13、 with appropriate drift sizeP/U stand on derrickM/U BHA as follow:12-1/4 BIT+12-1/4 NBRR+1 x 8-1/2 DC+12-1/4 STRR+8x8-1/2 DC+8-1/2 Jar+2 x 8-1/2 DC+X/O+15 x 5 HWDP,五、三开作业,RIH:,RIH to 1100.Wash down gently from 1100 and tag TOC or Float Collar+/1122.Record TOC depth in IADC Report Pick up 5-10 feet a
14、bove plug.Test casing with water to 1500 psi Drill out Cement,Plug,Float Collar and cement inside shoe-track to 1195(10 above shoe)Circulate hole to clean water.Test casing string(above shoe)to 1500 psi Displace hole to 58 PCF Diesel-Emulsion mud Drill out remaining cement and clear pocket to 1210,五
15、、三开作业,Drill 12-1/4 Vertical hole from 1210 to+/-3225:,While drilling WASIA&SHUIBA formation,add MICA fine,Medium or Coarse to the 58 PCF mud in the tank Sweep hole with 40 bbls hivis every 90 drilled Drill hole as fast as possible-with WOB:40-50K lbs Do not pump water into this well from start to fi
16、nish Ream every tight spot properly Make connection as fast as possible,五、三开作业,DRILLING TO CSG POINT:,At+/-3225,circulate bottoms up with 150 bbls of Hivis pill POOH to shoe(1205)&RIH back to bottom(Wiper-trip)Circulate hole clean with 100 bbls Hivis pill 800 GPMCheck shaker screen to ensure hole is
17、 cleanSpot lubricated hivis pill to cover open hole Displace same with 19 bbls of mud Drop TOTCO SurveyPOOH to surface,五、三开作业,RUN CASING:,Change Rams&Test as per Aramco Standard R/U 9-5/8 casing equipment:Casing Power Tong,Casing Slips,Bushing,Circulating Head,ElevatorHPJSMP/U Shoe&Float Collar(tack
18、 weld)&test with waterRun 9-5/8 casing as per Casing List.Baker lock first 4 jointsCall Halliburton Man&FMN when pick up DVFill up Casing every joint for first 5 joints with 58 PCF Mud Use TDS.Then fill every 15 jts(+/-45 bbl)RIH to setting depth.Make up Cementing HeadCirculate 3 x bottoms up with 5
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- 钻井 现场 施工 指令

链接地址:https://www.desk33.com/p-1275141.html